ServiceTitan ImplementationStatus report for Scott Cummings
Prepared by Amanda Foran
Updated Tuesday 20 October 2026

Where the implementation stands

Live status, what has been completed since the last update on 6 October, and what happens next.

Go live
12 November 2026
23 days from today. Date unchanged and on track
Current phase
Sign offs and training
Six of seven workstream demos held. Accounting sign offs now with the new Head of Finance
Training guides
Wed 21 Oct
Jake sends the written guides for every workflow except payroll
Next milestone
Thu 22 Oct
Payroll demo with Sunny, and the training logistics call to set the training week

The road to go live

Discovery
Jul to 16 Aug
Complete
Pricebook
Aug to early Oct
Loaded
Demos
13 to 15 Oct, payroll 22 Oct
6 of 7 held
Sign offs and training
Now to early Nov
Under way
Final data pull
Mon 9 Nov
Requested
Go live
Thu 12 Nov
Confirmed

The work behind the numbers

6 of 7
Workstream demos held 13 to 15 October. Payroll moved to 22 October so Sunny can join
8
Residential install kits built from our own quotes and supplier codes, checked by Jamie and accepted by ServiceTitan
450,000+
QuoteSoft materials loaded into a construction estimate in under a minute
$4.41M
Receivables migrated at 24 August, a 100% tie to QuickBooks. Sign off is the last step
33
Accounting and payroll decisions packaged into four short sign off sheets for Sunny

Completed since the last update

Demos

  • Accounting and Memberships on 13 October, Demand Service and Service Agreements on 14 October, Residential Installs and Commercial Construction on 15 October
  • Fixes from the demos are in: tax on purchase orders now shows correctly at 8% or 13%, every business unit can take card payments, and change orders show on the continuation sheet
  • Terms and conditions added to the retail install and construction quote templates on 19 October, using Jeff Armstrong's wording
  • The team has started the ServiceTitan Academy courses ahead of hands on training

Installs and pricing

  • Install kits built from every install quote in Service Fusion since January 2025, matched to the parts we buy most from Boone and Master Group. Jamie confirmed them and ServiceTitan accepted them on 8 October
  • Jeff Armstrong's package summaries and dual fuel, ERV and HRV pricing delivered on 7 October. Membership pricing to show on every install quote
  • Derrick set the time and material rates on 13 October: $110 an hour, $75 truck charge and 40% markup on materials
  • Warehouse ordering template has what it needs from Boone, with Daikin copper being added
  • Mastron confirmed fully built. Marden goes in as a single sheet metal line, since that is how they bill

People and setup

  • Every technician checked against the agreed business units and roles. Construction crew moved to Installer, departed staff removed
  • Default labour type set for every technician from Scott Clements' chart on 14 October
  • New Internal Property Holdings business unit added for the rental properties
  • Shared service manager login created, so managers can close jobs from the office
  • Dispatch board teams set up so the office can filter by crew
  • Robert Koop and Riley Brazeau added with their rates. Sunny Singh set up as an Admin on 19 October
  • Staff positions corrected so each person gets the right Academy courses

Accounting and data

  • Four sign off sheets for Sunny covering the ledger map, classes and tax, receivables and the go live data, and payroll codes
  • QuickBooks connection mapping and test exports under way with Jake and Alex
  • Service Fusion asked to pull the full sales history, all attachments and the file showing which job each attachment belongs to, as of Monday 9 November
  • Backup ready if Service Fusion is late: the sales history pulled a week at a time and merged. ServiceTitan confirmed that layout works for their import
  • Historical job photos are part of that request, so they come across at go live
Demos are done, bar payroll. All six were run in the live system on the real pricebook. What came up in them has already been fixed or is in the list below. Payroll is this Thursday so our new Head of Finance can see it first hand.
Sunny Singh started as Head of Finance on 19 October. He is taking over the controller role, so the accounting and payroll decisions now go to him rather than sitting with Alex. They are packaged into four short sheets so he can work through them quickly. Jake is giving him a ServiceTitan accounting overview on Wednesday.
Pricebook Pro cancellation. ServiceTitan raised a termination fee on the add on we cancelled before using. We have told them in writing that we are not paying one and asked for written confirmation that nothing will be billed. Their management is reviewing it.
QuickBooks Desktop needs an upgrade. The office copy is the 2023 version and has to be upgraded to get bank feeds back. Jake says the effect on ServiceTitan is light, a new connector once it is done, but the timing should be set with him so it does not land in go live week.

Demo schedule

DateDemoStatus
Tue 13 OctAccountingHeld
Tue 13 OctMembershipsHeld
Wed 14 OctDemand ServiceHeld
Wed 14 OctService AgreementsHeld
Thu 15 OctResidential InstallsHeld
Thu 15 OctCommercial ConstructionHeld
Thu 22 OctPayroll, moved from 16 October so Sunny can attendBooked

Where each part of the project sits

Counts are from ServiceTitan's shared project log as Jake last updated it on 13 October. Several of his open items have since been closed by email. The right hand column is where each area actually stands today.

AreaDoneOpenWaitingWhere it stands today
Pricebook610Suppliers in, Mastron confirmed, Marden as one line. Last piece is the HVAC equipment import, with ServiceTitan
Demand Service1541Demo held. Teams, shared manager login and card payments done. Business unit emails answered today: a shared mailbox is fine
Payroll1320Labour type set for every technician. Three new labour codes need setting up in QuickBooks. Demo Thursday
Accounting801Demo held, tax fix in. Ledger and class decisions with Sunny. Connection testing with Jake and Alex this week
Commercial Construction620Demo held. QuoteSoft materials load straight into estimates, terms on quotes, change orders working
Residential Installs640Demo held. Install kits, package summaries and pricing all delivered, so three of Jake's four open items are done. Quote approval wording is with Scott Clements
Memberships722Demo held. Plans and import built. Discounts still to decide
Service Agreements521Demo held. Time and material rates set by Derrick. Two and three visit template wording still to come
Data320Go live export requested from Service Fusion for 9 November, backup tested. Commercial customer duplicates still to decide

The last pieces of the puzzle

Everything else is in place. These are the items between here and go live, each with an owner.

ItemWhat's neededWith
Accounting sign offsAnswers on the four sheets: ledger map, classes and tax, receivables and go live data, payroll codes. Includes who signs off the receivables tie and who approves the QuickBooks connection on the live fileSunny
QuickBooks set upCreate the three new labour items, rename 400-010 to Plumbing Service Labour, and write off the three Winmar Lanark balances before the final reloadAlex and Sunny
QuickBooks upgradeUpgrade from the 2023 version and set the timing with Jake so the new connector is in before go live weekAlex and Sunny
Quote approval wordingDrop "a copy of which is attached" from the quote wording, and decide whether service quotes get their own terms or lose the referenceScott Clements
Membership discountsDecide whether a membership discount applies only to the covered equipment or across other work tooLisa and Scott
Commercial customersDecide whether the restoration and property accounts become one customer per company with a location per site, or stay as one customer per claimLisa, Scott and Alex
Training weekSet the hands on training dates on Thursday's logistics call with ServiceTitan's trainerLisa, Scott and Amanda
Service Fusion exportWritten confirmation that the export team will deliver everything on the morning of 9 November. Asked again todayService Fusion
Pricebook ProWritten confirmation that the add on is cancelled with no feeServiceTitan
Vendor invoicesSuppliers copying invoices to the ServiceTitan AP address so bills create themselves in both systemsClimate Works
One window to plan for. The final data pull is Monday 9 November and go live is Thursday 12 November, so anything booked in those few days gets entered in both systems. It is a known, short double entry period and the team will be told exactly how to handle it.

The plan, week by week

DateWhat happensStatus
Tue 20 OctQuickBooks connection mapping and test exports, Jake and AlexBooked
Wed 21 OctJake sends the written training guides. ServiceTitan accounting overview for Sunny and Alex at 2pmBooked
Thu 22 OctTraining logistics call at 11am. Payroll demo with SunnyBooked
W/c 26 OctSunny's sign offs back. QuickBooks items set up and mapping finishedPlanned
Late Oct to early NovHands on training on the configured system, dates set on 22 OctoberPlanned
Mon 9 NovFinal data pull: Service Fusion sales and attachments, and the QuickBooks customer list, transaction list and receivables aging, all as of that dayRequested
Thu 12 NovGo liveConfirmed